Englewood East MSBU Bridge Rehabilitations - Construction

Project Description

Englewood East MSBU has 5 bridges needing design and construction services to implement the FDOT maintenance and repair items for each of the respective bridges.

This project is for bridge rehabilitation construction -   

Gulfstream Blvd. over Memorial Waterway - Bridge #014083

Marathon Blvd. over Sioux Waterway - Bridge #014084

Gulfstream Blvd. over Sea Mist Waterway - Bridge #014091

Wilmington Blvd. over Gondolier Waterway - Bridge #014096

Ocean Spray Blvd. over March Waterway - Bridge #014097

Project Location

Gulfstream Blvd. over Memorial Waterway - Bridge #014083

Marathon Blvd. over Sioux Waterway - Bridge #014084

Gulfstream Blvd. over Sea Mist Waterway - Bridge #014091

Wilmington Blvd. over Gondolier Waterway - Bridge #014096

Ocean Spray Blvd. over March Waterway - Bridge #014097

See Location Map

Latest Updates

This project is complete.

Budget

Phase Cost
Design $187,020
Construction $1,047,835.95
Funding source(s): Englewood East MSBU

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 02/10/2023 04/10/2023
Design Development 06/07/2023 03/15/2024
Construction 09/03/2024 03/17/2025 01/23/2025

Supporting Materials

Project Phase
Project Complete

Last Updated
03/14/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Kimley-Horn Engineers

Construction Contractor
Villa Fuerte Construction