Midway Boulevard Bridge over North Spring Lake - Bridge #014073 Construction

Project Description

Hurricane Ian damaged this bridge, we have to modify our existing design contract to include storm-related repairs.

The Midway Bridge over North Spring Lake (#014073) requires engineering services to provide minor rehabilitation and maintenance to the bridge structure. 

Project Location

The bridge is located on Midway Boulevard just southwest of US 41 over North Spring Lake.

Latest Updates

Upcoming Project Activities - March 2025

Construction bids were opened on March 3, 2025, and Thomas Marine Construction was the lowest bidder.  The contract is on the Board of County Commissions' agenda for approval on April 8, 2025.

Budget

Phase Cost
Design $88,735.05
Construction $983,435
Funding source(s): Road and Bridge (Gas Tax)

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 10/07/2021 09/09/2022

Project Phase
Construction

Last Updated
03/14/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Project Number
2021002053

Sponsor Department
Public Works

Design Engineer/Architect
HDR

Construction Contractor
Thomas Marine Construction